16/11/18. The two 50 yard greens are done, now onto the first 75yd target green. |
![]() |
16/11/18. Greens looking great , single cut done today.
|
15/11/18. Bankings being turfed , first 50 yard green now completed. |
15/11/18. Thin covering of sand is put down levelled out and now turf is being laid. |
14.11.18. Topsoil now on top of the sub soil , this is raked out tramped and stones removed. |
12/11/18. Soil for target greens coming out of our 10th quarry on Hawkshill . Total of 5,500 ton of soil carted up . |
13/11/18. Some greens are starting to show up nicely.![]() |
6/11/18. Foundation soil getting placed on location of new target greens. |
5/11/18. Removing turf from range where target greens are going. |
![]() |
5/11/18. New range in the background coming on. |
![]() |
5/11/18. A lot of work removing all the turf from the green areas , but this will save money as turf will be put back onto bankings around new greens. |
![]() |