10/1/18. First of all the Greenstaff would like to wish all the members a Happy New Year and hope you all have a good season .
This is our first Drainage job this Winter it is the 18th fairway on Swailend .
|
11/1/18. First we cleared a gap in the tress then set about the task with a 6 ton digger hired in from PTM plant hire. |
12/1/18. We are steadily working along track which started at the 11th path. |
12/1/18. As we work along the drain , the staff lay 2 inches of 10mm pea crete along the bottom of track to form a gravel bed in which to lay the pipes on . |
23/1/18. 15th Approach on Swailend getting the works , 16 lateral drains linked into main drain . This area for years has been extremely wet , but not anymore. Total metres of drains was 280m |
30/1/18. We are now working at the 16th Fairway on Swailend , as you can see from picture there was some big stones in the way. |