20/2/17 Swailend 4th tee getting screening boards put in . |
20/2/17 Swailend 4th tee soil getting added up to level of boards. |
8/2/17. Hawkshill 5th greenside bunker ( one on the right before green) . New face being built. |
2/2/17. This was a big task , but staff were up to the challenge and worked hard to have all drains dug out , pipe installed and filled up with stones in 1 week . Great effort ! |
These two notices are in clubhouse notice boards for your info |
Adverse weather Policy. |
10/2/17. 5th greenside bunker on Hawkshill , face is now complete and ready for turfing around the top. |
10/2/17. looking good. This will prevent stones falling off face and ending up in the bunker sand. |
10/2/17. Greenside bunker on left of 5th hole Hawkshill . Old face was getting rather high after years of edging , new face getting put in to help make bunker more appealing and easier to maintain. |
15.2/17. Deputy Head Stephen Brown applying another liquid Winter turf hardener. . |
15/2/17, Final box tee at 9th Hawkshill getting screened. |
16/2/17. 5th bunker Hawkshill greenside , the revetted face now completed. Also greens getting another deep spike . |
16/2/17. 5th bunker Hawkshill , one that's 20 yards back from green now completed. |
21/2/17. 2nd hole on Hawkshill , turf getting laid back down . |
20/2/17. Greens on Hawkshill getting a roll and cut after the spiking . |
20/2/17. Greens looking good for this time of year. |
21/2/17. Staff doing a great job with the 2nd hole turfing work, a lot of turf to lay down. |