17/3/17. Blocked drain between the 1st green and pond on Hawkshill. Problem was identified by the two bunkers at green  being full of water  . Pipe that goes into pond was checked with drain rods to discover a blockage . so immediate action was taken to fix it.

17/3/17, Water bubbling out from drainage stones.

17/3/17. Water was coming into the hole so quick we had to pump water out to inspect fault . The pipe was blocked and blockage cleared. We now just need to fix pipe connection and fill the hole up and re turf .
20/3/17. Drain at 18th on Swailend  in rough had to get sorted as a stone drain collapsed . New lateral was also put in to catch water along tree edge.

20/3/17 . New terra spike machine out giving Swailend greens a decent aerate to relieve compaction in the rootzone .